By Carrie Ciciotte
ELLSWORTH—Although there might not be enough money to
complete the federal portion of the Union River dredging
project, the U.S. Army Corps of Engineers is going full steam
ahead with the project.
According to Project Manager Mark Habel, the Corps awarded
the $1.4 million contract Nov. 1 to Burnham and Associates of
Salem, Mass.
"The contractor issued an order to proceed," Habel
said.
The dredging equipment is mounted on barges in Boston Harbor
but now they face a new obstacle: the weather.
Habel said the small craft have 250 miles of open ocean to
cross.
"They are all small craft so they have to wait for good
weather," Habel said. "I’ve got my fingers crossed
and hopefully they’ll be working sometime next week."
Hopes for a timely start for the Union River dredging project
hit some rocky water this October. The lack of a bid within 25
percent of the project’s estimated cost prevented the project
from beginning Nov. 1, its original estimated start date.
Dredging can only occur between Nov. 1 and April 15 because
of federal regulations protecting salmon-spawning grounds.
The Army Corps of Engineers sent out requests for bids in
August. Only one company, Burnham and Associates of Salem,
replied.
At $1.4 million, that estimate was $350,000 over the roughly
$1 million the corps had expected it to cost.
Habel hoped that the corps and Burnham and Associates could
have narrowed the gap between the two figures.
Even if the company could perform the work for a lower amount
of money, funding might still be a problem. Congress only
allocated $900,000 for the project.
The Ellsworth project was lucky to get that. Earlier this
year the Army Corps of Engineers eliminated the funding for the
Union River project from its funding request. Rep. John
Baldacci, D-Maine, said he worked to restore federal funds for
the Ellsworth project.
He said the Union River project is necessary for commercial
and recreational boating in the area.
Habel is hopeful that the extra funds needed to complete the
project will be awarded by Congress later.
"We’ll see how far we can get this year," he
said.
According to Doug Dunbar, a spokesman for Baldacci, the
congressman plans to do all he can to make sure the federal
government does its part to ensure the project’s completion.
The federal money does not include the dredging of the city
harbor.
The cost of the city harbor dredging is estimated to be
$250,000 and will be paid for by the city.
"We thought it would be in the neighborhood of $250,000
to $300,000," said Ellsworth City Manager Tim King.
"We have to negotiate that separately with the contractor.
We’ve been in contact with our city engineer to make those
arrangements."
The city’s engineering firm of Woodard and Curran is
soliciting proposals to do the city’s portion of the project.
"There’s no rush on that. We’re more concerned about
getting a good price from a good contractor," King said.
"The city’s dredge can’t occur until the federal dredge
is completed."
The city’s dredge will be around the outside perimeter of
the harbor which King said begins approximately at Indian Point
and ends prior to the Union River Bridge.
The federal money would dredge 3.75 miles of river providing
a 5-foot-deep channel. According to Baldacci, an estimated
60,000 cubic yards of material would be removed from the Union
River. King said the dredged material will be deposited at
Tinker’s Ridge in the Union River Bay.
The Fiscal Year 2001 Veterans, Housing and Urban Development,
Energy and Water Appropriations Conference Report also included
$1 million for waterfront development in Bangor.